在空调器安装中
移机操作步骤
Operation steps of relocation
在空调器安装中,有很多时候是移拆旧机异地安装。空调器的移机安装与新机第一次安装, 在步骤上略有不同,其步骤如下:
In the installation of air conditioners, the old machines are often
removed and installed in different places. The moving installation of
the air conditioner is slightly different from the first installation of
the new one, and the steps are as follows:
1. 开机检查空调器制冷、制热、送风等运行状态,确认效果良好是否正常。
1. Start up and check the operation status of refrigeration, heating and
air supply of the air conditioner to confirm whether the effect is good
and normal.
2. 确认效果良好后,进行收氟操作,然后断掉电源。
2. After confirming that the effect is good, carry out fluorine collection operation, and then cut off the power supply.
3. 拆下室内、外机电源线、信号线和连接管。注意保持连接管接口的清洁,并用胶带包裹好接头螺母和喇叭口。
3. Remove the power lines, signal lines and connecting pipes of indoor
and outdoor units. Pay attention to keep the connecting pipe interface
clean, and wrap the joint nut and bell mouth with adhesive tape.
4. 撬开过墙孔,将连接管、电源线、信号线和排水管抽出。抽管方向要合理,保证不损坏连接管,并将连接管、电源线、信号线和排水管分开,然后弯管收拢。
4. Pry through the wall hole and pull out the connecting pipe, power
line, signal line and drainage pipe. The direction of pipe drawing shall
be reasonable to ensure that the connecting pipe is not damaged, and
the connecting pipe, power line, signal line and drainage pipe shall be
separated, and then the elbow shall be closed.
5. 从安装板上取下室内机,然后拆下安装板。取室内机时,应保持室内机右端稍高,让冷凝水从另一端流出室外。
5. Remove the indoor unit from the mounting plate, and then remove the
mounting plate. When taking the indoor unit, keep the right end of the
indoor unit slightly higher and let the condensate flow out of the room
from the other end